1. Basic Work Rate
- Formula:
If A completes a work in (x) days:
RA=x1Combined rate:
Rtotal=RA+RB+⋯- Example: A can complete a work in 12 days and B in 18 days. How long will they take together? Solution:
Therefore:
T=5/361=536=7.2 days2. Efficiency & Substitution
- Formula:
If efficiency ratio is (a:b), time ratio is:
b:a- Example: A is 50% more efficient than B. B takes 30 days alone. How many days will they take together? Solution: A’s efficiency:
Therefore time ratio:
A:B=2:3B takes 30 days, so A takes:
30×32=20 daysTogether:
T=20+3020×30=12 days3. Work Done in a Given Number of Days
- Formula:
If A completes work in (x) days, work done in (d) days:
xd- Example: A completes a work in 15 days. What fraction of the work does A complete in 6 days? Solution:
4. Remaining Work After Partial Completion
- Formula:
- Example: A completes a work in 12 days. After working alone for 4 days, B joins and they finish the remaining work in 3 days. Find B’s individual time. Solution: A’s rate:
Work done by A in 4 days:
124=31Remaining:
1−31=32A and B together complete (\frac23) in 3 days:
RA+B=32/3=92Therefore B’s rate:
92−121=368−363=365B’s time:
536=7.2 days5. Finding Individual Time from Combined Time
- Formula: If A and B take (x) and (y) days:
Hence:
T=x+yxy- Example: A takes 8 days and A+B together take 4.8 days. Find B’s time. Solution:
Therefore:
B=12 days6. Alternate Working Days
- Formula:
If A starts, calculate complete 2-day cycles first and then check the final day.
- Example: A takes 10 days and B takes 15 days. They work on alternate days, starting with A. When is the work completed? Solution: Work in 2 days:
After 10 days:
5×61=65Remaining:
61Day 11 is A’s turn:
101Remaining:
61−101=151Day 12 is B’s turn, and B completes:
151Therefore work finishes on:
12th day7. Alternate Working with Unequal Final Day
- Formula: Calculate work completed in complete cycles, then:
- Example: A completes a work in 6 days and B in 8 days. They work alternately starting with A. Find the completion time. Solution: Work in 2 days:
After 6 days (3 cycles):
3×247=87Remaining:
81Day 7 is A’s turn. A’s rate:
61Time required:
1/61/8=43 dayTotal:
643 days8. Men-Days / Workforce Problems
- Formula: For the same work:
More generally:
Work∝Men×Dayswhen all workers have equal efficiency.
- Example: 8 men complete a work in 15 days. How many days will 12 men take? Solution:
9. Men-Women-Children Workforce Equations
- Formula: Convert different workers into equivalent units using their efficiency ratio. If 1 woman does the work of (k) men:
Then use:
Equivalent workers×Days=Constant- Example: 2 women can do the work of 1 man. If 6 men complete a work in 10 days, how many days will 4 men and 4 women take? Solution: 4 women are equivalent to:
So total equivalent workers:
4+2=6Since 6 men take 10 days:
10 days10. Workforce Change During a Project
- Formula:
Calculate completed and remaining work separately when workers join or leave.
- Example: 8 men complete a work in 15 days. After 5 days, 4 more men join. How many additional days are required? Solution: Total work:
Work completed in 5 days:
8×5=40Remaining:
120−40=80New workforce:
8+4=12Required days:
1280=632 days11. Workers Leaving During a Project
- Formula:
- Example: 12 men can complete a work in 20 days. After 8 days, 4 men leave. How many more days are required? Solution: Total work:
Work completed:
12×8=96Remaining:
240−96=144Remaining workers:
12−4=8Days required:
8144=18 days12. Wages Based on Work Done
- Formula:
If workers have equal efficiency:
Wage ratio=Work ratio- Example: A, B and C work for 6, 4 and 5 days respectively at equal efficiency. If the total wage is ₹3,600, find A’s share. Solution: Work ratio:
Total:
15A’s share:
3600×156=₹144013. Wages Based on Efficiency × Time
- Formula:
- Example: A works 6 days at efficiency 2 units/day, while B works 4 days at efficiency 3 units/day. If ₹2,400 is distributed according to work, find their shares. Solution: A’s work:
B’s work:
3×4=12Ratio:
1:1Each gets:
₹120014. Efficiency Ratio and Time Ratio
- Formula:
If A is (x%) more efficient than B:
EA:EB=(100+x):100- Example: A is 25% more efficient than B. If B takes 20 days, how many days does A take? Solution:
Therefore:
TA:TB=4:5 TA=20×54=16 days15. Work Equivalence from Efficiency
- Formula:
Therefore:
E1T1=E2T2for the same amount of work.
- Example: A is twice as efficient as B. If A works for 6 days, how many days must B work to complete the same amount of work? Solution:
Thus:
2EB×6=EB×T T=12Therefore:
12 daysAdvanced Variants
16. A, B and C Working Together
- Formula:
Hence:
T=RA+RB+RC1- Example: A, B and C can complete a work in 12, 18 and 36 days respectively. How long will they take together? Solution:
Therefore:
6 days17. One Worker Joins or Leaves at a Specific Time
- Formula:
For each phase:
W=R×T- Example: A completes a work in 12 days and B in 18 days. A works alone for 3 days, then B joins. Find the total completion time. Solution: A’s rate:
Work in 3 days:
123=41Remaining:
43Combined rate:
121+181=365Time for remaining work:
5/363/4=43×536=527=5.4Total:
3+5.4=8.4 days18. Pipes and Workers Combined
- Formula: Treat every entity as a work rate:
- Example: A worker completes a job in 10 days. A machine completes it in 15 days. A faulty process removes (\frac1{30}) of the work per day. How long do they take together? Solution:
Therefore:
T=215=7.5 days19. Work Completed by Alternating Groups
- Formula: Calculate the work of each cycle:
Then determine complete cycles and the remaining work.
- Example: A can finish a work in 8 days and B in 12 days. A works for 2 days, B for 1 day repeatedly. How long will the work take? Solution: Work in one 3-day cycle:
After 2 cycles (6 days):
32Remaining:
31A needs:
1/81/3=38days.
Total:
6+38=832 days20. Work and Wages with Different Efficiencies
- Formula:
Do not use only the number of days when efficiencies differ.
- Example: A works for 5 days at efficiency 3 units/day and B works for 6 days at efficiency 2 units/day. Total wage is ₹2,100. Find A’s share. Solution: A’s work:
B’s work:
6×2=12Ratio:
15:12=5:4A’s share:
2100×95=₹1166.67B’s share:
₹933.33Premium Content
Unlock Work and Time Concepts and all premium lessons with a subscription.
From ₹199.99/year — See plans